Edison Athletics

Scope of Work:
New football stadium consisting of new bleachers, press box, and all-weather track; baseball field, softball field, multi-use fields, and swimming pool improvements.  The Design firm selected for this project is Verde Design.

Status:
Programming with new field configurations are almost complete.  Currently evaluating conceptual estimates to compare against original budgets.  Targeting construction start of the stadium late Spring / Summer 09. In addition, the District has also hired design professionals for the site topographic and utility surveys; geotechnical investigations; and CEQA process, which are all currently underway.

Athletic Improvement Program

October 30, 2008
Verde Design has been developing the standards for the Athletic Improvements and presenting information to the district including, pool standards and artificial turf standards. Verde has also been developing the standards for field lighting and bleachers at all sites. Verde is currently working on the Schematic Design Phase and is currently scheduled to be complete with that phase in November 2008. The District has selected Robert A. Bothman, Inc. as the Lease/Leaseback contractor for the athletic improvements. A Pre-Construction Services agreement has been signed by the District and is currently being processed. Bothman will begin assisting the architect with project review in November 2008. Athletic improvements are scheduled to begin construction in summer 2009 at Chavez, Edison, and Stagg. These projects will be phased at each site due to constraints with other projects; the first phase will be football field and track improvements.

Meeting Minutes Verde
5-21-08.pdf
6-04-08.pdf
Revised Agenda 0604.pdf
6-25-08.pdf
7-23-08.pdf

Edison Modernization

Scope:
Construction of a new two-story administration/classroom building to replace classes currently housed in portable classrooms, construction of new industrial arts building and a lunch shelter replacement. 

Convert the existing administration wing into classrooms, renovation of the existing science labs, renovation of the library, renovation of the existing performing arts building and band/music building.  In addition the existing Main Gymnasium building, pool building, north & south gym buildings, wrestling room, and girls and boys lockers room will be renovated.  The student quad area will be redeveloped to include a raised platform.

Site parking lots will be upgraded and new staff parking will be added off Charter way and a new student drop-off and bus loop will be added.  New fencing to improve campus security is also included.
The Architectural firm selected for this project is MVE Institutional, Inc.


Status:
October 30, 2008
The architect, MVE Institutional, is currently preparing the Programming Document for Measure Q scope of work, as well as a campus Master Plan that will coordinate both Measure Q and Measure C scope of work to ensure proper integration and sequencing. Weekly meetings have included the administrative staff and teachers. A Master Site Schedule is being developed, and the pre-design phase should be complete within the next few months. The District has also selected a Lease/Leaseback contractor, Roebbelen, to perform pre-construction support services for the architect, including estimating and constructability review.


Meeting Minutes MVE
5-21-08.pdf
5-28-08.pdf
6-4-08.pdf
6-11-08.pdf
6-18-08.pdf
7-2-08.pdf
7-9-08.pdf
7-16-08.pdf
Edison Exhibits
Exhibit 06-18-08 - Existing admin bldg-option 1.pdf
Exhibit 06-18-08 - Industrial Arts.pdf
Exhibit 06-18-08 - Industrial Arts-Future Science.pdf
Exhibit 06-18-08 - New classroom-admin bldg-lower floor.pdf
Exhibit 06-18-08 - New classroom-admin bldg-upper floor.pdf
Exhibit 06-18-08 - Site Plan.pdf
Exibit 06-18-08 - Existing admin bldg-option 2.pdf
SUSD_Edison Master Plan Agenda 6-18-08.pdf

Existing admin bldg-072908.pdf
New classroom-admin bldg_enlarged-072908.pdf
New classroom-admin bldg_ground floor-072908.pdf
New classroom-admin bldg_upper floor-072908.pdf
Site Plan_07-30-08.pdf
Vocational art bldg-072908.pdf

 

   Select a project below
 » Chavez  » Stagg
 » Edison  » Walton
 » Franklin  
  Quick Strike
» K8 Play Field and Hard Court Renovations
» Portable Replacements

It's a great time
to do business with SUSD


SUSD was a gold sponsor of the 2008 State of the City event held Thursday, Feb. 28 at the Port of Stockton. Many business people, as well as current and former educators stopped by our booth to talk about the recent passage of Measure Q. The Community Relations Office provided folders of information to business executives and contractors, who will be enlisted to help us renovate and repair our school sites over the next 15 years. Mayor Ed Chavez, the Yes on Q committee chairman, mentioned Measure Qís passage as an example of the cityís coming together for our youth during his final State of the City speech. Watch the PowerPoint presentation (5.6 MB pdf) shown to those who stopped by our booth.

Measure Q passes
with 67.75% of the vote!!!


February 5, 2008, was a monumental day in the history of Stockton Unified School District. Measure Q, the $464.5 million construction bond, passed overwhelmingly. The next 10 to 12 years will see major renovations coming to our campuses.

Everyone associated with the Measure Q campaign would like to thank the numerous volunteers, especially those students, who helped make phone calls, place doorhangers and walk precincts. It was a total team effort to get Measure Q passed, and now the work begins to renovate and modernize our many elementary and high school campuses.

Look for opportunities to serve on site level committees that will help us plot out exactly how our district will look for many years to come.

Measure Q Bond Overview

High School Details

Elementary School Details

Edison Proposed Modernization Design


Measure C Citizens Bond Oversight Committee

Members: Rhonda Finister, Venice Holladay, Ted Leland, Ron Paoletti, Kathy Piper, Kitty Ruhstaller, Gene Acevedo, Angel Jimenez

Expenditures (PDF)

 

© 2008 SUSD   |   SITE MAP  |  STREET DICTIONARY  |  HOME  |  BACK TO TOP